Update of IT modernization Project

The Latest Position Of Implementation Is As Follows: 

  • Primary Data Centre has been deployed and started functioning at Navi Mumbai since 3rd April, 2013. Disaster Recovery Centre has been powered on at Mysore on 15-05-15. System Integrators have started commissioning process.
  • 27647 Departmental Post offices including mail offices and administrative offices have been networked at single Wide Area Network (WAN) and connected to Data Centre.
  • Core Banking Solution (CBS) has been rolled out in 3416 Post Offices including 800 HOs.
  • ATMs have been installed in 123 locations.
  • Core Insurance solution (CIS-PLI) has been rolled out in 13976 Post Offices.
  • Rural Hardware vendor has been finalized and contract has been signed. Supply of Rural Hardware devices in Pilot BOs will start in November 2015.
  • Common Infrastructure Solutions (Wave 1) roll out is under progress.
    • Installation of Antivirus (AV) completed in 18700 locations.
    • Installation of Active Directory (AD) is in progress and deployed in 15800 locations.
    User Acceptance Test (UAT) for Wave 2 & 3 solutions along with CSI-FSI Integration is completed.
    • Pilot rollout is scheduled from 31st Sep 2015.
    • CSI trainings have been completed for pre pilot locations.
    Rural System Integrator (RSI) is kicked off on 5th May 2015.
    • Software Requirements Specification (SRS) has been approved.
    • UAT is planned in Nov 2015.
    Procurement planned through DGS&D includes
    • Handheld devices for mail delivery in post offices.
    • Hardware for processing of mails in sorting offices.